About Upgrade
|
|
================
|
|
|
|
ScyllaDB upgrade is a rolling procedure - it does not require a full cluster
|
|
shutdown and is performed without any downtime or disruption of service.
|
|
|
|
To ensure a successful upgrade, follow
|
|
the :doc:`documented upgrade procedures <upgrade-guides/index>` tested by
|
|
ScyllaDB. This means that:
|
|
|
|
* You should follow the upgrade policy:
|
|
|
|
* Starting with version **2025.4**, upgrades can skip minor versions as long
|
|
as they remain within the same major version (for example, upgrading directly
|
|
from 2025.1 → 2025.4 is supported).
|
|
* For versions **prior to 2025.4**, upgrades must be performed consecutively—
|
|
each successive X.Y version must be installed in order, **without skipping
|
|
any major or minor version** (for example, upgrading directly from 2025.1 → 2025.3
|
|
is not supported).
|
|
* You cannot skip major versions. Upgrades must move from one major version to
|
|
the next using the documented major-version upgrade path.
|
|
* You should upgrade to a supported version of ScyllaDB.
|
|
See `ScyllaDB Version Support <https://docs.scylladb.com/stable/versioning/version-support.html>`_.
|
|
* Before you upgrade to the next version, the whole cluster (each node) must
|
|
be upgraded to the previous version.
|
|
* You cannot perform an upgrade by replacing the nodes in the cluster with new
|
|
nodes with a different ScyllaDB version. You should never add a new node with
|
|
a different version to a cluster - if you
|
|
:doc:`add a node </operating-scylla/procedures/cluster-management/add-node-to-cluster>`,
|
|
it must have the same X.Y.Z (major.minor.patch) version as the other nodes in
|
|
the cluster.
|
|
|
|
Upgrading to each patch version by following the Maintenance Release Upgrade
|
|
Guide is optional. However, we recommend upgrading to the latest patch release
|
|
for your version before upgrading to a new version.
|
|
|