doc: remove wrong image upgrade info (5.x.y-to-5.x.y)
This commit removes the invalid information about the recommended way of upgrading ScyllaDB images (by updating ScyllaDB and OS packages in one step) from the 5.x.y-to-5.x.y upgrade guide. This upgrade procedure is not supported (it was implemented, but then reverted). Refs https://github.com/scylladb/scylladb/issues/15733 In addition, the following files are removed as no longer necessary (they were only created to incorporate the (invalid) information about image upgrade into the upgrade guides. /upgrade/_common/upgrade-image-opensource.rst /upgrade/_common/upgrade-guide-v5-patch-ubuntu-and-debian-p1.rst /upgrade/_common/upgrade-guide-v5-patch-ubuntu-and-debian-p2.rst /upgrade/_common/upgrade-guide-v5-patch-ubuntu-and-debian.rst
This commit is contained in:
@@ -1,68 +0,0 @@
|
||||
Upgrade Guide - |SCYLLA_NAME| |SRC_VERSION| to |NEW_VERSION| for |OS|
|
||||
======================================================================
|
||||
|
||||
This document is a step-by-step procedure for upgrading from |SCYLLA_NAME| |FROM| to |SCYLLA_NAME| |TO|, and rollback to 2021.1 if required.
|
||||
|
||||
|
||||
Applicable Versions
|
||||
------------------------
|
||||
This guide covers upgrading |SCYLLA_NAME| from version |FROM| to version |TO| on |OS|. See :doc:`OS Support by Platform and Version </getting-started/os-support>` for information about supported versions.
|
||||
|
||||
|
||||
Upgrade Procedure
|
||||
----------------------------
|
||||
|
||||
.. note::
|
||||
Apply the following procedure **serially** on each node. Do not move to the next node before validating the node is up and running the new version.
|
||||
|
||||
A ScyllaDB upgrade is a rolling procedure which does **not** require full cluster shutdown.
|
||||
For each of the nodes in the cluster, you will:
|
||||
|
||||
* Drain node and backup the data.
|
||||
* Check your current release.
|
||||
* Backup configuration file.
|
||||
* Stop ScyllaDB.
|
||||
* Download and install new ScyllaDB packages.
|
||||
* Start ScyllaDB.
|
||||
* Validate that the upgrade was successful.
|
||||
|
||||
|
||||
**During** the rolling upgrade it is highly recommended:
|
||||
|
||||
* Not to use new |TO| features.
|
||||
* Not to run administration functions, like repairs, refresh, rebuild or add or remove nodes.
|
||||
* Not to apply schema changes.
|
||||
|
||||
Upgrade steps
|
||||
-------------------------------
|
||||
Drain node and backup the data
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
Before any major procedure, like an upgrade, it is recommended to backup all the data to an external device. In ScyllaDB, backup is done using the ``nodetool snapshot`` command. For **each** node in the cluster, run the following command:
|
||||
|
||||
.. code:: sh
|
||||
|
||||
nodetool drain
|
||||
nodetool snapshot
|
||||
|
||||
Take note of the directory name that nodetool gives you, and copy all the directories having this name under ``/var/lib/scylla`` to a backup device.
|
||||
|
||||
When the upgrade is complete (all nodes), the snapshot should be removed by ``nodetool clearsnapshot -t <snapshot>``, or you risk running out of space.
|
||||
|
||||
|
||||
Backup configuration file
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo cp -a /etc/scylla/scylla.yaml /etc/scylla/scylla.yaml.backup-5.x.z
|
||||
|
||||
Gracefully stop the node
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo service scylla-server stop
|
||||
|
||||
Download and install the new release
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
Before upgrading, check what version you are running now using ``dpkg -s scylla-server``. You should use the same version in case you want to |ROLLBACK|_ the upgrade. If you are not running a |FROM| version, stop right here! This guide only covers |FROM| to |TO| upgrades.
|
||||
@@ -1,84 +0,0 @@
|
||||
**To upgrade ScyllaDB:**
|
||||
|
||||
#. Update the |APT|_ to |NEW_VERSION|.
|
||||
#. Install:
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo apt-get update
|
||||
sudo apt-get dist-upgrade scylla
|
||||
|
||||
Answer ‘y’ to the first two questions.
|
||||
|
||||
Start the node
|
||||
^^^^^^^^^^^^^^^^
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo service scylla-server start
|
||||
|
||||
Validate
|
||||
^^^^^^^^^^^^^^^^
|
||||
#. Check cluster status with ``nodetool status`` and make sure **all** nodes, including the one you just upgraded, are in UN status.
|
||||
#. Use ``curl -X GET "http://localhost:10000/storage_service/scylla_release_version"`` to check the ScyllaDB version.
|
||||
#. Check the scylla-server log (execute ``journalctl _COMM=scylla``) and ``/var/log/syslog`` to validate there are no errors.
|
||||
#. Check again after 2 minutes, to validate no new issues are introduced.
|
||||
|
||||
Once you are sure the node upgrade is successful, move to the next node in the cluster.
|
||||
|
||||
Rollback Procedure
|
||||
-----------------------
|
||||
|
||||
.. include:: /upgrade/_common/warning_rollback.rst
|
||||
|
||||
The following procedure describes a rollback from ScyllaDB release |TO| to |FROM|. Apply this procedure if an upgrade from |FROM| to |TO| failed before completing on all nodes. Use this procedure only for nodes you upgraded to |TO|.
|
||||
|
||||
ScyllaDB rollback is a rolling procedure which does **not** require full cluster shutdown.
|
||||
For each of the nodes rollback to |FROM|, you will:
|
||||
|
||||
* Drain the node and stop ScyllaDB.
|
||||
* Downgrade to previous release.
|
||||
* Restore the configuration file.
|
||||
* Restart ScyllaDB.
|
||||
* Validate the rollback success.
|
||||
|
||||
Apply the following procedure **serially** on each node. Do not move to the next node before validating the node is up and running with the new version.
|
||||
|
||||
Rollback steps
|
||||
------------------------
|
||||
Gracefully shutdown ScyllaDB
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
.. code:: sh
|
||||
|
||||
nodetool drain
|
||||
sudo service scylla-server stop
|
||||
|
||||
Downgrade to previous release
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
Install:
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo apt-get install scylla=5.x.y\* scylla-server=5.x.y\* scylla-jmx=5.x.y\* scylla-tools=5.x.y\* scylla-tools-core=5.x.y\* scylla-kernel-conf=5.x.y\* scylla-conf=5.x.y\*
|
||||
|
||||
Answer ‘y’ to the first two questions.
|
||||
|
||||
Restore the configuration file
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo rm -rf /etc/scylla/scylla.yaml
|
||||
sudo cp -a /etc/scylla/scylla.yaml.backup-5.x.z /etc/scylla/scylla.yaml
|
||||
|
||||
Start the node
|
||||
^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo service scylla-server start
|
||||
|
||||
Validate
|
||||
^^^^^^^^^^^^^^^^^^
|
||||
Check upgrade instruction above for validation. Once you are sure the node rollback is successful, move to the next node in the cluster.
|
||||
@@ -1,2 +0,0 @@
|
||||
.. include:: /upgrade/_common/upgrade-guide-v5-patch-ubuntu-and-debian-p1.rst
|
||||
.. include:: /upgrade/_common/upgrade-guide-v5-patch-ubuntu-and-debian-p2.rst
|
||||
@@ -1,47 +0,0 @@
|
||||
There are two alternative upgrade procedures:
|
||||
|
||||
* :ref:`Upgrading ScyllaDB and simultaneously updating 3rd party and OS packages <upgrade-image-recommended-procedure>`. It is recommended if you are running a ScyllaDB official image (EC2 AMI, GCP, and Azure images), which is based on Ubuntu 20.04.
|
||||
|
||||
* :ref:`Upgrading ScyllaDB without updating any external packages <upgrade-image-upgrade-guide-regular-procedure>`.
|
||||
|
||||
.. _upgrade-image-recommended-procedure:
|
||||
|
||||
**To upgrade ScyllaDB and update 3rd party and OS packages (RECOMMENDED):**
|
||||
|
||||
Choosing this upgrade procedure allows you to upgrade your ScyllaDB version and update the 3rd party and OS packages using one command.
|
||||
|
||||
#. Update the |SCYLLA_REPO|_ to |NEW_VERSION|.
|
||||
|
||||
#. Load the new repo:
|
||||
|
||||
.. code:: sh
|
||||
|
||||
sudo apt-get update
|
||||
|
||||
|
||||
#. Run the following command to update the manifest file:
|
||||
|
||||
.. code:: sh
|
||||
|
||||
cat scylla-packages-<version>-<arch>.txt | sudo xargs -n1 apt-get install -y
|
||||
|
||||
Where:
|
||||
|
||||
* ``<version>`` - The ScyllaDB version to which you are upgrading ( |NEW_VERSION| ).
|
||||
* ``<arch>`` - Architecture type: ``x86_64`` or ``aarch64``.
|
||||
|
||||
The file is included in the ScyllaDB packages downloaded in the previous step. The file location is ``http://downloads.scylladb.com/downloads/scylla/aws/manifest/scylla-packages-<version>-<arch>.txt``
|
||||
|
||||
Example:
|
||||
|
||||
.. code:: sh
|
||||
|
||||
cat scylla-packages-5.1.2-x86_64.txt | sudo xargs -n1 apt-get install -y
|
||||
|
||||
.. note::
|
||||
|
||||
Alternatively, you can update the manifest file with the following command:
|
||||
|
||||
``sudo apt-get install $(awk '{print $1'} scylla-packages-<version>-<arch>.txt) -y``
|
||||
|
||||
.. _upgrade-image-upgrade-guide-regular-procedure:
|
||||
@@ -1,16 +1,14 @@
|
||||
.. |OS| replace:: EC2, GCP, and Azure
|
||||
.. |ROLLBACK| replace:: rollback
|
||||
.. _ROLLBACK: ./#rollback-procedure
|
||||
.. |SRC_VERSION| replace:: 5.x.y
|
||||
.. |NEW_VERSION| replace:: 5.x.z
|
||||
.. |FROM| replace:: 5.x.y
|
||||
.. |TO| replace:: 5.x.z
|
||||
.. |SCYLLA_NAME| replace:: ScyllaDB Image
|
||||
.. |PKG_NAME| replace:: scylla
|
||||
.. |SCYLLA_REPO| replace:: ScyllaDB deb repo
|
||||
.. _SCYLLA_REPO: https://www.scylladb.com/download/?platform=ubuntu-20.04&version=scylla-5.0
|
||||
.. |APT| replace:: ScyllaDB deb repo
|
||||
.. _APT: http://www.scylladb.com/download/
|
||||
.. include:: /upgrade/_common/upgrade-guide-v5-patch-ubuntu-and-debian-p1.rst
|
||||
.. include:: /upgrade/_common/upgrade-image-opensource.rst
|
||||
.. include:: /upgrade/_common/upgrade-guide-v5-patch-ubuntu-and-debian-p2.rst
|
||||
======================================================================
|
||||
Upgrade Guide - ScyllaDB Image (EC2, GCP, Azure) 5.x.y to 5.x.z
|
||||
======================================================================
|
||||
|
||||
|
||||
If you are running a ScyllaDB official image (for EC2 AMI, GCP, or Azure), you
|
||||
need to:
|
||||
|
||||
* Download and install the new ScyllaDB release for Ubuntu. See
|
||||
the :doc:`upgrade guide for Ubuntu <upgrade-guide-from-5.x.y-to-5.x.z-ubuntu>`
|
||||
for instructions.
|
||||
* Update underlying OS packages.
|
||||
|
||||
See :doc:`Upgrade ScyllaDB Image </upgrade/ami-upgrade>` for details.
|
||||